[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107920":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107920,783,1,"单选题","审核承包人编制的施工组织设计，是项目监理机构在施工阶段采取的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":14},"B","经济措施",{"key":19,"text":20,"correct":21},"C","技术措施",true,{"key":23,"text":24,"correct":14},"D","合同措施","考点:投资控制的措施。项目监理机构在施工阶段采取的技术措施包括：（1）对设计变更进行技术经济比较，严格控制设计变更；（2）继续寻找通过设计挖潜节约投资的可能性；（3）审核承包人编制的施工组织设计，对主要施工方案进行技术经济分析。参见教材P6。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]