[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107919":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107919,783,1,"单选题","从（ ）上采取措施，包括明确项目组织结构，明确投资控制者及其任务，以使项目投资控制有专人负责，明确管理职能分工。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织",true,{"key":16,"text":17,"correct":18},"B","技术",false,{"key":20,"text":21,"correct":18},"C","经济",{"key":23,"text":24,"correct":18},"D","管理","考点:投资控制的措施。投资控制的组织措施包括明确项目组织结构，明确投资控制者及其任务，以使投资控制有专人负责，明确管理职能分工。参见教材P5。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]