[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107914":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107914,783,1,"单选题","做好工程施工记录、保存各种信息档案，参与处理索赔事宜，属于施工阶段投资控制的（ ）措施。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","组织",false,{"key":16,"text":17,"correct":14},"B","经济",{"key":19,"text":20,"correct":14},"C","技术",{"key":22,"text":23,"correct":24},"D","合同",true,"考点:投资控制的措施。合同措施：（1）做好工程施工记录，保存各种文件图纸，特别是注有实际施工变更情况的图纸，注意积累素材，为正确处理可能发生的索赔提供依据。参与处理索赔事宜。（2）参与合同修改、补充工作，着重考虑它对投资控制的影响。参见教材P6。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]