[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107913":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107913,783,1,"单选题","工程变更款项最终结算时，应以（ ）为依据。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","经建设单位同意的暂定价格",false,{"key":16,"text":17,"correct":18},"B","建设单位与施工单位达成的协议",true,{"key":20,"text":21,"correct":14},"C","实际发生的款项",{"key":23,"text":24,"correct":14},"D","竣工结算款","考点:我国项目监理机构在建设工程投资控制中的主要工作。工程变更款项最终结算时，应以建设单位与施工单位达成的协议为依据。参见教材P9。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]