[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107907":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107907,783,1,"单选题","下列措施中，属于施工阶段投资控制组织措施的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制投资控制工作流程",true,{"key":16,"text":17,"correct":18},"B","参与合同修改",false,{"key":20,"text":21,"correct":18},"C","审核竣工结算",{"key":23,"text":24,"correct":18},"D","对变更方案进行技术经济分析","考点:建设工程投资控制的原理。组织措施：（1）在项目监理机构中落实从投资控制角度进行施工跟踪的人员、任务分工和职能分工。（2）编制本阶段投资控制工作计划和详细的工作流程图。选项A属于组织措施；选项B、C、D，分别对应于合同、经济和技术措施。参见教材P6。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]