[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107889":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107889,783,1,"单选题","下列费用中，属于建设工程静态投资部分的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基本预备费",true,{"key":16,"text":17,"correct":18},"B","涨价预备费",false,{"key":20,"text":21,"correct":18},"C","建设期利息",{"key":23,"text":24,"correct":18},"D","运营期利息","考点:建设工程项目投资的概念。固定资产投资（工程造价）=静态投资部分+动态投资部分。其中，静态投资部分包括建筑安装工程费、设备及工器具购置费、工程建设其他费和基本预备费。参见教材P1。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]