[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107886":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107886,783,1,"单选题","某建设项目，建筑安装工程费为40000万元，设备工器具费为5000万元，建设期利息为1400万元，工程建设其它费用为4000万元，建设期预备费为9500万元（其中基本预备费为4900万元），项目的铺底流动资金为600万元。则该项目的动态投资部分的金额为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6000",true,{"key":16,"text":17,"correct":18},"B","6600",false,{"key":20,"text":21,"correct":18},"C","11500",{"key":23,"text":24,"correct":18},"D","59900","考点:建设工程项目投资的概念。建设投资=静态投资部分+动态投资部分。其中，动态投资部分主要包括涨价预备费和建设期利息。因此，其动态投资部分的金额＝（9500-4900）+1400＝6000（万元）。参见教材P1。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]