[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107882":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107882,783,1,"单选题","对于某精密机床加工制造企业的办公楼而言，在其建设工程总投资中，不应包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","涨价预备费",false,{"key":16,"text":17,"correct":14},"B","基本预备费",{"key":19,"text":20,"correct":14},"C","建设期利息",{"key":22,"text":23,"correct":24},"D","铺底流动资金",true,"考点:建设工程项目投资的概念。建设工程项目总投资是指为完成工程项目建设并达到使用要求或生产条件，在建设期内预计或实际投入的全部费用总和。生产性建设工程项目总投资包括建设投资、建设期利息和流动资金三部分；非生产性建设工程项目总投资包括建设投资和建设期利息两部分。其中建设投资和建设期利息之和对应于固定资产投资。本题中属于非生产性建设工程，不包含流动资金。参见教材P1。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]