[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107874":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107874,783,1,"单选题","定额单价法编制施工图预算的过程包括：①计算工程量；②套用定额单价，计算工料机费用；③按费用定额取费，并汇总造价；④工料分析；⑤准备资料，熟悉施工图纸。正确的排列顺序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","④⑤②①③",false,{"key":16,"text":17,"correct":14},"B","④⑤①②③",{"key":19,"text":20,"correct":14},"C","⑤②①③④",{"key":22,"text":23,"correct":24},"D","⑤①②④③",true,"考点:施工图预算的编制方法。定额单价法编制施工图预算的过程包括：编制前的准备工作；熟悉图纸和预算定额以及单位估价表；了解施工组织设计和施工现场情况；划分工程项目和计算工程量；套单价；工料分析；计算主材费；按费用定额取费；计算汇总工程造价；复核；编制说明、填写封面。参见教材P121。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]