[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107868":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107868,783,1,"单选题","“总预算＝∑单位建筑工程费用＋∑单位设备及安装工程费用＋工程建设其他费用＋预备费＋建设期利息＋铺底流动资金”描述的是（ ）预算编制中的（ ）总预算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","二级.建设项目",false,{"key":16,"text":17,"correct":18},"B","二级.单项工程",true,{"key":20,"text":21,"correct":14},"C","三级.建设项目",{"key":23,"text":24,"correct":14},"D","三级.单项工程","考点:施工图预算的编制方法。施工图预算在逐级汇总的基础上，可有二级或三级编制形式；算式是将单位工程汇总，并形成最终单项工程的总预算（B）。如果拥有完整的单位工程、单项工程、建设项目，则为三级预算。参见教材P124。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]