[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107866":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107866,783,1,"单选题","设计概算应按编制时（ ）的价格水平编制，总投资应完整地反映编制时建设项目实际投资。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目所在地",true,{"key":16,"text":17,"correct":18},"B","施工单位所在地",false,{"key":20,"text":21,"correct":18},"C","建设单位所在地",{"key":23,"text":24,"correct":18},"D","监理单位所在地","考点:设计概算的审查。设计概算应按编制时项目所在地的价格水平编制，总投资应完整地反映编制时建设项目实际投资。参见教材P116。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]