[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107864":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107864,783,1,"单选题","确定和控制建设项目全部投资的文件是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","总概算表",false,{"key":16,"text":17,"correct":14},"B","项目可行性研究报告",{"key":19,"text":20,"correct":21},"C","建设项目设计概算",true,{"key":23,"text":24,"correct":14},"D","建设项目施工概算","考点:设计概算的内容和编制依据。建设项目设计概算是设计文件的重要组成部分，是确定和控制建设项目全部投资的文件，是编制固定资产投资计划、实行建设项目投资包干、签订承发包合同的依据，是签订贷款合同、项目实施全过程造价控制管理以及考核项目经济合理性的依据。参见教材P111。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]