[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107861":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107861,783,1,"单选题","利用扩大单价法编制单位建筑工程概算时，在收集原始资料后，应进行的工作有：①计算工程量；②各项费用计算；③套用扩大单价；④计算单位工程概算造价。其正确顺序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","③—①—②—④",false,{"key":16,"text":17,"correct":18},"B","①—③—②—④",true,{"key":20,"text":21,"correct":14},"C","③—②—①—④",{"key":23,"text":24,"correct":14},"D","①—②—③—④","考点:设计概算编制办法。利用扩大单价法（又称概算定额法）编制单位建筑工程概算时，其主要步骤包括：列项，计算工程量；确定扩大单价，计算人料机三费；计取相关费用；计算单位工程概算造价等。参见教材P114。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]