[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107856":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107856,783,1,"单选题","下列有关价值工程中，功能价值分析的说法中，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在功能成本法中，V＞1即功能现实成本大于功能评价值",false,{"key":16,"text":17,"correct":18},"B","在功能成本法中，V＜1时，可能存在功能过剩",true,{"key":20,"text":21,"correct":14},"C","在价值指数法中，V＞1时，一般都要列入改进对象",{"key":23,"text":24,"correct":14},"D","在价值指数法中，V＞1即评价对象成本大于功能比重","考点:价值工程的应用。选项A错误，在功能成本法中，V＜1即功能实现成本大于功能评价值；选项C错误，在价值指数法中，V＞1时，对象在技术、经济等方面具有某些特征，在客观上存在着功能很重要而消耗的成本却很少的情况，这种情况一般不列入改进对象。参见教材P108。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]