[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107851":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107851,783,1,"单选题","价值工程中的全寿命周期费用是指（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","生产过程发生的全部成本",false,{"key":16,"text":17,"correct":14},"B","从开始使用至报废过程中发生的费用总和",{"key":19,"text":20,"correct":14},"C","产品存续期的总成本",{"key":22,"text":23,"correct":24},"D","生产费用、使用费用之和",true,"考点:价值工程方法。价值工程是以提高产品或作业价值为目的，通过有组织的创造性工作，寻求用最低的寿命周期成本，可靠地实现使用者所需功能的一种管理技术。参见教材P100。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]