[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107838":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107838,783,1,"单选题","在采用定额单价法编制施工图预算的过程中，套用定额单价时，发现分析工程施工工艺条件与预算单价不一致，则应当（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","直接套用",false,{"key":16,"text":17,"correct":14},"B","换算预算价格",{"key":19,"text":20,"correct":21},"C","调量不调价",true,{"key":23,"text":24,"correct":14},"D","编制补充单位估价表","考点:施工图预算的编制方法。定额单价法编制施工图预算以及套用定额单价（预算单价）的过程中，发现工程施工工艺条件与定额单价（设定条件）不一致，应当调量不调价；两者完全相同，直接套用；两者品种或规格不同，换算价格。参见教材P122。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]