[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107835":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107835,783,1,"单选题","在新方案创造中，组织者将问题函寄专家后获得反馈意见，整理分析后再函寄，直到得出新方案。这属于（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","强制确定法",false,{"key":16,"text":17,"correct":14},"B","头脑风暴法",{"key":19,"text":20,"correct":14},"C","哥顿法",{"key":22,"text":23,"correct":24},"D","德尔菲法",true,"考点:价值工程的应用。在备选答案中，强制确定法（A）是功能评价、确定功能重要程度的方法；后三个选项，属于新方案创造的方法，但只有D符合题意。参见教材P110～111。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]