[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107829":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107829,783,1,"单选题","实物量法编制施工图预算时，计算工程量后紧接着进行的工作是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","套定额单价，计算人材机费用",false,{"key":16,"text":17,"correct":18},"B","套消耗定额，计算人材机消耗量",true,{"key":20,"text":21,"correct":14},"C","汇总人材机费用",{"key":23,"text":24,"correct":14},"D","计算管理费等其他各项费用","考点:施工图预算的编制方法。实物量法编制施工图预算的步骤为：准备资料、熟悉施工图纸；计算工程量；套用消耗定额，计算人料机消耗量；计算并汇总人工费、材料费、机具使用费；计算其他各项费用，汇总造价；复核；编制说明、填写封面。参见教材P123～124。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]