[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107824":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107824,783,1,"单选题","设计概算一经批准一般不得进行调整，其总投资反映（ ）时的价格水平。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目立项",false,{"key":16,"text":17,"correct":14},"B","可行性研究",{"key":19,"text":20,"correct":21},"C","概算编制",true,{"key":23,"text":24,"correct":14},"D","项目施工","考点:设计概算的审查。设计概算应按编制时项目所在地的价格水平编制，总投资应完整地反映编制时建设项目的实际投资。参见教材P116。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]