[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107811":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107811,783,1,"单选题","根据《建设工程工程量清单计价规范》GB 50500－2013的规定，在合同约定之外的或者因变更而产生的、工程量清单中没有相应项目的零星额外工作应列入（ ）中。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","暂估价",false,{"key":16,"text":17,"correct":14},"B","暂列金额",{"key":19,"text":20,"correct":21},"C","计日工",true,{"key":23,"text":24,"correct":14},"D","措施项目费","考点:工程量清单编制。在工程量清单编制以及其他项目清单中，计日工是为了解决现场发生的零星工作的计价而设立的。计日工适用的零星工作一般是指合同约定之外的或者因变更而产生的、工程量清单中没有相应项目的额外工作，尤其是那些时间不允许事先商定价格的额外工作。参见教材P133。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]