[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107810":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107810,783,1,"单选题","对受委托编制的工程量清单，应有造价工程师签字、盖章，还应有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","造价咨询人盖章",true,{"key":16,"text":17,"correct":18},"B","招标单位法定代表人盖章",false,{"key":20,"text":21,"correct":18},"C","编制人盖章",{"key":23,"text":24,"correct":18},"D","负责审核的造价工程师盖章","考点:工程量清单计价。对受委托编制的工程量清单，应有造价工程师签字、盖章以及工程造价咨询人盖章。参见教材P135。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]