[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107809":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107809,783,1,"单选题","当招标人仅要求总包人对其发包的专业工程进行现场协调和统一管理、对竣工资料进行统一汇总整理等服务时，总承包服务费按发包的专业工程估算造价的（ ）左右计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.5%",true,{"key":16,"text":17,"correct":18},"B","2.5%",false,{"key":20,"text":21,"correct":18},"C","3.5%",{"key":23,"text":24,"correct":18},"D","3.0%","考点:招标控制价及确定方法。当招标人仅要求总包人对其发包的专业工程进行现场协调和统一管理、对竣工资料进行统一汇总整理等服务时，编制总承包服务费按发包的专业工程估算造价的1.5%左右计算。参见教材P140。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]