[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107808":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107808,783,1,"单选题","投标人投标报价时应依据（ ）确定清单项目的综合单价。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工图中的图示工程量",false,{"key":16,"text":17,"correct":14},"B","实际施工的项目特征",{"key":19,"text":20,"correct":14},"C","设计图纸",{"key":22,"text":23,"correct":24},"D","招标工程量清单项目的特征描述",true,"考点:投标报价审核方法。投标人投标报价时应依据招标工程量清单项目的特征描述确定清单项目的综合单价。参见教材P142。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]