[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107804":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107804,783,1,"单选题","总价合同是以（ ）为依据，由发承包方经过协商确定的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","招标控制价和设计图纸",false,{"key":16,"text":17,"correct":14},"B","工程量清单和工程说明书",{"key":19,"text":20,"correct":21},"C","设计图纸和工程说明书",true,{"key":23,"text":24,"correct":14},"D","工程量清单和招标控制价","考点:合同计价方式。总价合同是指支付给承包方的工程款项在承包合同中是一个规定的金额。它是以设计图纸和工程说明书为依据，由承包方与发包方经过协商确定的。参见教材P146。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]