[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107801":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107801,783,1,"单选题","关于固定总价合同特点的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同执行过程中，由于市场因素造成工料成本增加，合同总价可进行相应调整",false,{"key":16,"text":17,"correct":14},"B","合同执行过程中，工程量与招标文件不符时，合同总价可进行相应调整",{"key":19,"text":20,"correct":14},"C","合同执行过程中，发包方承担主要风险，合同总价通常偏低",{"key":22,"text":23,"correct":24},"D","合同执行过程中，承包方承担主要风险，合同总价通常偏高",true,"考点:合同计价方式。采用固定总价合同，合同总价只有在设计和工程范围发生变更的情况下才能随之作相应的变更，除此之外，合同总价一般不得变动。因此，采用固定总价合同，承包方要承担合同履行过程中的主要风险，要承担实物工程量、工程单价等变化而可能造成损失的风险。参见教材P146。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]