[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107799":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107799,783,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500-2013）的规定，关于编制招标控制价的说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","国有资金投资的建设工程招标，招标人可以不编制招标控制价",false,{"key":16,"text":17,"correct":18},"B","暂估价中专业工程金额应按招标工程量清单中列出的金额填写",true,{"key":20,"text":21,"correct":14},"C","暂估价如招标工程量清单未列出金额或单价时，编制招标控制价时可以不予考虑",{"key":23,"text":24,"correct":14},"D","总承包服务费应由招投标双方协商确定","考点:招标控制价及确定方法。选项A，国有资金投资的建设工程招标，招标人必须编制招标控制价；选项C，暂列金额、暂估价如招标工程量清单未列出金额或单价时，编制招标控制价时必须明确；选项D，总承包服务费应按照省级或行业建设主管部门的规定计算，或参考相关规范计算。参见教材P140。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]