[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107797":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107797,783,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500-2013）的规定，下列关于其他项目费的审核说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂估价不得变动和更改",true,{"key":16,"text":17,"correct":18},"B","暂列金额应按照招标工程量清单中列出的金额填写，必要时可以变动",false,{"key":20,"text":21,"correct":18},"C","计日工应按照施工图中的图示工程量，自主确定综合单价并计算计日工金额",{"key":23,"text":24,"correct":18},"D","总承包服务费应按照投标人提出协调.配合与服务要求和施工现场管理需要自主确定","考点:投标报价审核方法。暂估价不得变动和更改。选项B，暂列金额应按照招标工程量清单中列出的金额填写，不得变动。选项C，计日工应按照招标工程量清单列出的项目和估算的数量，自主确定综合单价并计算计日工金额。选项D，总承包服务费应根据招标工程量列出的专业工程暂估价内容和供应材料、设备情况，按照招标人提出协调、配合与服务要求和施工现场管理需要自主确定。参见教材P142。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]