[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107796":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107796,783,1,"单选题","关于工程量清单招标方式下，投标人报价的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专业工程暂估价中的专业工程应由投标人自主确定价格并计入报价",false,{"key":16,"text":17,"correct":18},"B","暂估价中的材料应按暂估单价计入综合单价",true,{"key":20,"text":21,"correct":14},"C","措施项目中的总价项目应包括规费和税金",{"key":23,"text":24,"correct":14},"D","投标人报价时可以给予一定幅度的总价优惠","考点:投标报价审核方法。选项A，在投标价的编制与审核中，专业工程暂估价必须按照招标工程量清单中列出的金额填写；选项C，措施项目中的总价项目应采用综合单价方式报价，包括除规费、税金外的全部费用；选项D，投标人在进行工程项目工程量清单招标的投标报价时，不能进行投标总价优惠。参见教材P142。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]