[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107794":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107794,783,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500-2013）的规定，下列有关投标报价的审核内容说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","暂列金额应按照招标工程量清单中列出的金额填写，但是有必要时可以变动",false,{"key":16,"text":17,"correct":14},"B","专业工程暂估价由投标人自主报价",{"key":19,"text":20,"correct":14},"C","在施工中，出现风险内容及其范围在招标文件规定的范围内时，合同价款可以调整",{"key":22,"text":23,"correct":24},"D","措施项目费中的安全文明施工费不作为竞争性费用",true,"考点:投标报价审核办法。选项A，暂列金额应按照招标工程量清单中列出的金额填写，不得变动；选项B，专业工程暂估价必须按照招标工程量清单中列出的金额填写；选项C，在施工中，出现风险内容及其范围在招标文件规定的范围内时，合同价款不做调整。参见教材P142。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]