[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107793":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107793,783,1,"单选题","根据现行规定，除钢材、水泥等，其它材料价格涨幅超过投标报价时基准价格（ ）以上，由发包人承担其涨价风险。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3%",false,{"key":16,"text":17,"correct":18},"B","5%",true,{"key":20,"text":21,"correct":14},"C","10%",{"key":23,"text":24,"correct":14},"D","15%","考点:合同价款约定内容。根据现行规定，钢材、水泥等主要材料价格涨幅超过投标报价时3%、其它材料超过5%，由发包人承担其涨价风险。参见教材P152。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]