[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107791":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107791,783,1,"单选题","对于工程内容和技术经济指标规定很明确的项目，合同中列有调值条款，且工期在1年以上的适用（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可调总价合同",true,{"key":16,"text":17,"correct":18},"B","固定总价合同",false,{"key":20,"text":21,"correct":18},"C","成本加酬金合同",{"key":23,"text":24,"correct":18},"D","固定单价合同","考点:合同计价方式。可调总价合同适用于工程内容和技术经济指标规定很明确的项目，由于合同中列有调值条款，所以工期在1年以上的工程项目较适于这种合同计价方式。参见教材P147。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]