[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107787":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107787,783,1,"单选题","估算工程量单价合同，在最终工程结算时，工程量是以（ ）为计算依据。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际完成的工程量",true,{"key":16,"text":17,"correct":18},"B","招标人提供的清单工程量",false,{"key":20,"text":21,"correct":18},"C","施工图工程量",{"key":23,"text":24,"correct":18},"D","估算出的工程量","考点:合同计价方式。估算工程量单价合同，最后的工程结算价应按照实际完成的工程量来计算。参见教材P147。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]