[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107786":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107786,783,1,"单选题","某公建工程的施工图设计已经完成，且计划工期为24个月，其应采用（ ）合同。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","固定总价",false,{"key":16,"text":17,"correct":18},"B","可调总价",true,{"key":20,"text":21,"correct":14},"C","估计工程量单价",{"key":23,"text":24,"correct":14},"D","可调单价","考点:合同计价方式。公共建筑工程应当具有众多的潜在承包商，不宜采用成本加酬金合同；由于其施工图设计已经完成，可以采用总价合同。但由于工期长于1年，故采用可调整总价合同。参见教材P147。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]