[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107785":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107785,783,1,"单选题","根据《计价规范》的规定，对于合同工期较短、建设规模较小，技术难度较低，且施工图设计已审查完备的建设工程可以采用（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单价合同",false,{"key":16,"text":17,"correct":14},"B","可调单价合同",{"key":19,"text":20,"correct":21},"C","总价合同",true,{"key":23,"text":24,"correct":14},"D","成本价酬金合同","考点:合同计价方式。根据新《计价规范》，实行工程量清单计价的工程，应当采用单价合同。合同工期较短、建设规模较小，技术难度较低，且施工图设计已审查完备的建设工程可以采用总价合同；紧急抢险、救灾以及施工技术特别复杂的建设工程可以采用成本加酬金合同。参见教材P146。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]