[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107783":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107783,783,1,"单选题","（ ）的合同计价方式，承包方的实际成本实报实销，这不利于鼓励承包方降低成本，使得这种合同计价方式很少被采用。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","成本加奖罚",false,{"key":16,"text":17,"correct":14},"B","成本加固定酬金",{"key":19,"text":20,"correct":14},"C","最高限额成本加固定最大酬金",{"key":22,"text":23,"correct":24},"D","成本加固定百分比酬金",true,"考点:合同计价方式。成本加固定百分比酬金的合同计价方式，其工程总价及付给承包方的酬金随工程成本而水涨船高，这不利于鼓励承包方降低成本，正是由于这种弊病存在，使得这种合同计价方式很少被采用。参见教材P149。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]