[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107782":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107782,783,1,"单选题","下列成本加酬金合同计价形式中，最难以控制成本的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本加固定百分比酬金合同",true,{"key":16,"text":17,"correct":18},"B","成本加固定金额酬金合同",false,{"key":20,"text":21,"correct":18},"C","成本加奖罚合同",{"key":23,"text":24,"correct":18},"D","最高限额成本加固定最大酬金","考点:合同计价方式。成本加酬金合同中，承包方的实际成本实报实销。采用成本加固定百分比酬金计价，需要按照实际成本的固定百分比付给承包方一笔酬金。由于其工程总价及付给承包方的酬金随工程成本增加而增加，不利于鼓励承包方降低成本，故这种计价方式很少发包人被采用。参见教材P149。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]