[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107780":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107780,783,1,"单选题","根据《建设工程工程量清单计价规范》GB 50500－2013的规定，下列关于工程量清单的说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分部分项工程项目清单为可调整的闭口清单",false,{"key":16,"text":17,"correct":14},"B","暂估价只包括材料暂估价和工程设备暂估价",{"key":19,"text":20,"correct":21},"C","暂列金额是招标人暂定并包括在合同中的一笔款项",true,{"key":23,"text":24,"correct":14},"D","措施项目清单为不可调整清单","考点:工程量清单编制。选项A，分部分项工程项目清单为不可调整的闭口清单；选项B，暂估价包括材料暂估价、工程设备暂估价和专业工程暂估价；选项D，措施项目清单为可调整清单。参见教材P132。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]