[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107778":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107778,783,1,"单选题","根据《建设工程工程量清单计价规范》GB 50500－2013的规定，分部分项工程量清单中的工程数量是按照（ ）计算的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实体工程量的净值",true,{"key":16,"text":17,"correct":18},"B","设计文件结合不同施工方案确定的工程量平均值",false,{"key":20,"text":21,"correct":18},"C","工程实体量和损耗量之和",{"key":23,"text":24,"correct":18},"D","实际施工完成的全部工程量","考点:工程量清单编制。现行计量规范明确了清单项目的工程量计算规则，其工程量是以形成工程实体为准，并以完成后的净值来计算。参见教材P132。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]