[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107777":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107777,783,1,"单选题","根据《建设工程工程量清单计价规范》GB 50500－2013的规定，下列选项中属于工程量清单编制依据的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工图预算",false,{"key":16,"text":17,"correct":18},"B","建设工程设计文件",true,{"key":20,"text":21,"correct":14},"C","拟定的投标文件",{"key":23,"text":24,"correct":14},"D","非常规施工方案","考点:工程量清单编制。根据《建设工程工程量清单计价规范》，工程量清单编制的依据有：（1）现行计价规范和相关工程的国家计量规范；（2）国家或省级、行业建设主管部门颁发的计价定额和办法；（3）建设工程设计文件及相关资料；（4）与建设工程项目有关的标准、规范、技术资料；（5）拟定的招标文件；（6）施工现场情况、地勘水文资料、工程特点及常规施工方案；（7）其他相关资料。参见教材P130。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]