[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107775":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107775,783,1,"单选题","下列招标文件所列的工程量清单中，不可调整的闭口清单是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部分项工程量清单",true,{"key":16,"text":17,"correct":18},"B","能计量的措施项目清单",false,{"key":20,"text":21,"correct":18},"C","不能计量的措施项目清单",{"key":23,"text":24,"correct":18},"D","其他项目清单","考点:工程量清单编制。分部分项工程项目清单为不可调整的闭口清单。参见教材P130。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]