[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107774":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107774,783,1,"单选题","投标文件中已标明价格，经算数性错误修正（如有），且承包人已确认的工程量清单，称为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分部分项工程量清单",false,{"key":16,"text":17,"correct":14},"B","招标工程量清单",{"key":19,"text":20,"correct":14},"C","工程量清单计价表",{"key":22,"text":23,"correct":24},"D","已标价工程量清单",true,"考点:工程量清单概述。根据新《计价规范》的规定，工程量清单分为招标工程量清单和已标价招标工程量清单两大类型。已标价工程量清单指的是构成合同文件组成部分的投标文件中已标明价格，经算术性错误修正（如有）且承包人已确认的工程量清单，包括其说明和表格。参见教材P129。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]