[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107772":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107772,783,1,"单选题","根据《建设工程工程量清单计价规范》GB50500-2013，某分部分项工程的项目编码为01-02-03-004-005，其中“004”这一级编码的含义是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","附录分类顺序码",false,{"key":16,"text":17,"correct":14},"B","清单项目顺序码",{"key":19,"text":20,"correct":14},"C","分部工程顺序码",{"key":22,"text":23,"correct":24},"D","分项工程顺序码",true,"考点:工程量清单编制。分部分项工程和措施项目清单名称的阿拉伯数字标识。五级十二位 ◇一级：表示专业工程代码，两位 ◇二级：表示附录分类顺序码，两位 ◇三级：表示分部工程顺序码，两位 ◇四级：表示分项工程项目名称顺序码，三位 ◇五级：表示清单项目名称顺序编码，三位 前四级编码全国统一，第五级由招标人针对招标工程项目具体编制，从001起顺序编制，不得有重号。01 04 01 003×××。参见教材P131。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]