[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107771":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107771,783,1,"单选题","根据《建设工程量清单计价规范》（GB 50500-2013），下列关于工程量清单项目编码的说法中，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","第三级编码为分部工程顺序码，由三位数字表示",false,{"key":16,"text":17,"correct":18},"B","第五级编码应根据拟建工程的工程量清单项目名称设置，不得重码",true,{"key":20,"text":21,"correct":14},"C","同一标段含有多个单位工程，不同单位工程中项目特征相同的工程应采用相同编码",{"key":23,"text":24,"correct":14},"D","补充项目编码以“B”加上计算规范代码后跟三位数字表示，并应从001起顺序编制","考点:工程量清单编制。选项A，第三级为分部工程顺序码，05表示第5节现浇混凝土板；选项C，同一招标工程的项目不得重码；选项D，。参见教材P。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]