[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107770":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107770,783,1,"单选题","根据计量规范规定，不宜计量的措施项目费的通用计算方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","∑（措施项目工程量×措施项目综合单价）",false,{"key":16,"text":17,"correct":18},"B","∑（计算基数×相应费率）",true,{"key":20,"text":21,"correct":14},"C","∑（措施项目工程量×措施项目综合单价）+∑（单项措施费）",{"key":23,"text":24,"correct":14},"D","∑（措施项目项数×综合单价）","考点:工程量清单编制。对不能计量的措施项目（即总价措施项目），编制措施项目清单时，应按现行计量规范附录（措施项目）的规定执行。即∑（措施项目工程量×措施项目综合单价）。参见教材P132。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]