[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107769":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107769,783,1,"单选题","在编制招标控制价时，对于招标人自行供应材料的，总承包服务费一般可按招标人供应材料价值的（ ）考虑。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1%",true,{"key":16,"text":17,"correct":18},"B","1.5%",false,{"key":20,"text":21,"correct":18},"C","3%～5%",{"key":23,"text":24,"correct":18},"D","10%～15%","考点:招标控制价及确定方法。总包服务费，招标人自行供应材料、设备的，按招标人供应材料、设备价值的1%计算。参见教材P140。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]