[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107767":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107767,783,1,"单选题","根据《清单计价规范》，对于投标报价审核时，投标企业可以根据拟建工程的具体施工方案进行列项的清单是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部分项工程量清单",false,{"key":16,"text":17,"correct":18},"B","措施项目清单",true,{"key":20,"text":21,"correct":14},"C","其他项目清单",{"key":23,"text":24,"correct":14},"D","规费项目清单","考点:工程量清单编制。由于工程建设施工的特点和承包人组织施工生产的施工装备水平、施工方案及其管理水平的差异，同一工程、不同的承包人组织施工采用的施工措施并不完全一致，因此，措施项目清单应根据拟建工程的实际情况列项。参见教材P132。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]