[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107765":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107765,783,1,"单选题","作为估算工程量单价合同，结算工程最终价款的依据是合同中规定的分部分项工程单价和（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程量清单中提供的工程量",false,{"key":16,"text":17,"correct":14},"B","施工图中的图示工程量",{"key":19,"text":20,"correct":14},"C","合同双方商定的工程量",{"key":22,"text":23,"correct":24},"D","承包人实际完成的工程量",true,"考点:合同计价方式。这种合同形式是以工程量清单和相应的综合单价表为基础和依据来计算合同价格的，也称为计量估价合同。按合同中的分部分项工程单价和实际工程量，计算得出工程结算和支付的工程总价格。参见教材P148。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]