[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107764":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107764,783,1,"单选题","发包方只给出发包工程的有关分部分项工程以及工程范围，承包方填报相应的价格，最后按实际完成的工程数量进行结算，这属于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","可调单价合同",false,{"key":16,"text":17,"correct":14},"B","估算工程量单价合同",{"key":19,"text":20,"correct":21},"C","纯单价合同",true,{"key":23,"text":24,"correct":14},"D","固定价合同","考点:合同计价方式。采用纯单价合同时，发包方只向承包方给出发包工程的有关分部分项工程以及工程范围，不对工程量作任何规定。即在招标文件中仅给出工程内各个分部分项工程一览表、工程范围和必要的说明，而不必提供实物工程量。承包方在投标时只需要对这类给定范围的分部分项工程做出报价即可，合同实施过程中按实际完成的工程量进行结算。参见教材P148。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]