[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107762":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107762,783,1,"单选题","根据《计价规范》，关于招标控制价的描述中，正确的有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","招标控制价由分部分项工程费、措施项目费、其他项目费、规费和税金组成，不应包括招标文件中要求投标人承担的风险费用",false,{"key":16,"text":17,"correct":14},"B","国有资金投资项目的招标人可在招标文件中编制招标控制价或标底",{"key":19,"text":20,"correct":14},"C","招标控制价应在招标时公布，可以上调或下浮",{"key":22,"text":23,"correct":24},"D","招标人应招标控制价报工程所在地工程造价管理机构备查",true,"考点:招标控制价及确定方法。选项A，根据《计价规范》规定，招标控制价应包括招标文件中要求投标人承担的风险费用；选项B，国有资金投资项目必须编制招标控制价；选项C，招标人应在招标文件中如实公布招标控制价，不得对所编制的招标控制价进行上浮或下调。参见教材P139～140。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]