[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107761":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107761,783,1,"单选题","审核投标报价时，发现某标书漏填了分部分项工程量清单中“地面找平”一项的综合单价和合价，则正确处理方式是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","视为该项费用已包含在工程量清单的其他单价和合价中",true,{"key":16,"text":17,"correct":18},"B","认定该标书为废标",false,{"key":20,"text":21,"correct":18},"C","要求投标人就此项进行单独报价，补充到原报价书中",{"key":23,"text":24,"correct":18},"D","由工程师认定一个合理价格补充到原报价书中","考点:投标报价审核方法。未填写单价和合价的项目，视为此项费用已包含在已标价工程量清单中其他项目的单价和合价之中。参见教材P142。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]